Six people paint the fence and 15 hours how long would it take five workers to do the same job

Respuesta :

somaiasult2006
somaiasult2006 somaiasult2006
  • 02-01-2019
it will take 12.5 hrs for five workers to do the same job.


steps:

15 × 5 = 75

75 ÷ 6 = 12.5
Answer Link

Otras preguntas

Who vetoes bills? A.the president B.the Senate C.the attorney general D.the Speaker of the House
9. A change in color when two solutions are mixed together is a clue that a __has taken place. A.chemical change B.physical change C.temperature change D.change
what types of routes did the black death travel on
The temperature at the south pole was 6 degrees at 8am. At 3 pm it was -18 degrees. By how many degrees did the temperature drop?
Jamal is doing electronics engineering research and determines the result of his analysis can be expressed in terms of Complex Numbers. His result is (8-4i)(3i+
The Boy Scouts collected and stored three tons of old newspapers during a paper drive. They need to load them up to move them. If they carry 30 lb. at a time, a
PLEASE explain your answer! What is the value of q?
Need help don’t understand
which of the following would not be true of egyptian art?
What was one important achievement of Nelson Mandela? O A. He guided the process ending the Cold War. O B. He led the nonviolent Indian independence movement. O