A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

what is the greatest common factor of 42a^5b^3, 35a^3b^4, and 42ab^4? 7ab^3 6a^4b 42a^5b^4 77a^8b^7
what is the average rate of change for f(x)=x^2 9x=18 from x= -10 to x=10
round 12.091 to the nearest cent]
qué es "la natilla"?
Dodder (Cuscuta) is a plant that attaches itself to the acacia tree, wraps around it, absorbs nutrients from it, and makes it weak. What kind of an interspecies
expression for 7 more than y =
5p+9c=p solve for c I am confused on how to do it
the brain consists of 100 billion neuron and no two neurons are the same?
what is the meaning of the underline word suppliant of act i, scene i, of richard iii?
compare/contrast independent and dependent variables.