how do you find the mean completion time of a PERT network diagram?​

Respuesta :

okekesarah01642112
okekesarah01642112 okekesarah01642112
  • 02-01-2021

Answer:

PERT is an estimating technique that uses a weighted average of three numbers (see below) to come up with a final estimate. The resulting PERT estimate is calculated as (O + 4M + P)/6. This is called a "weighted average" since the most likely estimate is weighted four times as much as the other two values.

Answer Link

Otras preguntas

show all your work!Thank you!
In the fairytale, cinderella left behind a glass slipper as she fled the prince's ball at the stroke of midnight. the prince went from house to house in his kin
Which u.s. coastline has the greatest average loss due to erosion?
find the value of plz fast sin(100×π−π÷4)
In a right triangle, JKL, m<K=44. In right triangle PQR, m<Q=44. Which similarity postulate or theorem proves that JKL and PQR are similar? A. AA B. HL C.
does this look correct? Write the equation 9x+2y=6 in slope-intercept form. 2. 9x+2y=6 9x-9x+2y=6-9 x+2y=-3 x+2y/2=-3/2 x+y=-1.5
The length of a rectangle is 3131 inches greatergreater than twice the width. if the diagonal is 2 inches more than the​ length, find the dimensions of the rect
How did we get t^4/4 to t^3?
If the initial temperature of an ideal gas at 2.250 atm is 62.00 °C, what final temperature would cause the pressure to be reduced to 1.550 atm?
how many different ways can 5 students stand in a row